The comfort and safety of our residents and the neighbourhood is of the utmost importance and we will endeavour to address concerns throughout the process. We are committed to minimizing any inconveniences as much as possible.

Construction hours will adhere to the City of Toronto By-Law, between the hours of 7:00 a.m. to 7:00 p.m., weekdays, 9:00 a.m. to 5:00 p.m., Saturdays.

For information on permits, please visit:
http://app.toronto.ca/ApplicationStatus/setup.do?action=init

 


Latest updates:


In order to maintain site safety, we respectfully request that tenants and the public avoid walking through the construction area between High Park Avenue and Quebec Avenue and adhere to all safety and construction signage. It is considered trespassing and dangerous to do so as the area is active with construction vehicles and other operations.


June 1, 2017

Hoarding Installation
Hoarding will be installed in mid-June and the design will feature images of historical High Park.

 


August 31, 2017

Shoring and Excavation

On August 16, we received municipal approval for the shoring and excavation of the site. You will now see heavy equipment on site to commence the shoring and excavation of the project. It is anticipated that we will have excavated the two levels needed for new construction by late fall at which point we will bring in the crane and expect to be up to ground level by early 2018.

 

Hoarding and Site Protection

The hoarding is up and now features vintage postcard images of historical High Park along High Park and Quebec Avenues.

 

Existing Garage Rehabilitation

We have completed the re-waterproofing of the roof of the existing parking garage and new landscaping will follow.